National Arbitration Award on CBA Articles 7.2 versus 25 (2014)

Crossing occupational groups , higher level details , Overtime

return to Contract Database

National Arbitration on whether management must use overtime to cover a temporary vacancy in the maintenance craft instead of detailing an employee to a higher level assignment under the provisions of Article 25 and whether there is a violation of the National Agreement when an employee from a different occupational group is assigned higher level work on straight time, rather than assigning overtime to an employee within the same occupational group.

Document Type:  National Arbitration

APWU National Grievance Number:  Q00T4QC06082523

GATS Number:  Q00T-4Q-C 06082523

Craft:  Maintenance

Arbitrator Name: Shyam Das

Tags: Crossing occupational groups , higher level details , Overtime