This Step 4 Settlement Agreement addresses whether the installation of Neighborhood Collection and Delivery Box Units (NCDBU’s) and concrete slabs should be performed by maintenance craft employees instead of a private contractor. During our discussion, the parties agreed that if there are no time constraints and sufficient manpower is available, maintenance craft employees would be used to perform the work. However, it was their mutual understanding that if faced with problems such as time constraints, insufficient manpower, etc., management would take appropriate measures, including contracting out, to ensure completion of the work.
APWU National Grievance Number: H1T3AC29261
Subcontracting, NDCBU, NCDBU, Installing NCDBU, Installing NDCBU, Private Contractor