This Step 4 Settlement Agreement addresses whether an outside contractor should have been hired to repair the sprinkler system. After reviewing this matter, the parties mutually agreed that no national interpretive issue is fairly presented in this case, and that whether the proper action was taken was a local matter to be determined at the regional level based on the fact circumstances of this particular case using Chapter 530 of the ASM as a guide.
Document Type: Step 4 Agreement
APWU National Grievance Number: H4T2BC9553
Craft: Maintenance